Blasting is where opencast mining gets serious. One wrong hole depth or a missed warning siren, and the result is flyrock, a misfire or worse. That is exactly why DGMS and Mining Sirdar papers keep coming back to this chapter.
Here is the whole chapter in plain English: the explosives used, the accessories, the drilling terms, the safety routine around a blast, and what to do when a hole does not go off. If you want the legal side in more depth, keep our post on blasting safety regulations in open cast mining open in another tab.
1. Explosives Used in Opencast Mines
Four types are in common use: slurry explosive, ANFO (ammonium nitrate fuel oil), SMS (site mixed slurry) and SME (site mixed emulsion).
| Explosive | What it is |
|---|---|
| Slurry explosive | An oxygen-giving substance and a fuel mixed into a gel or jelly, with a sensitiser added. Non-cap-sensitive. Examples: Powergel, Supergel, Powerflo. |
| SMS (Site Mixed Slurry) | Oxidiser, fuel and sensitiser are mixed with a cross-linking agent, water and polymer. The ingredients ride in separate compartments of a truck and are mixed in a chamber on the truck, then poured into the hole. It turns into a gel soon after, and stemming follows. Non-cap-sensitive. |
| ANFO | Ammonium nitrate in porous prilled form, with diesel soaked deep into the prills. That raises its gas-producing power. Made from 94% ammonium nitrate and 6% diesel. |
| Emulsion explosive | The oxidiser (water-based) and the fuel (oil) are both liquid and do not mix on their own, so an emulsifying agent binds them. Two types: water-in-oil and oil-in-water. A special truck has separate chambers for water, oil and emulsifier, and the contents are mixed in a mixing chamber just before charging. |
Cap sensitive vs non-cap sensitive
- Cap sensitive: explodes from a detonator or detonating fuse. All explosives used underground are cap sensitive.
- Non-cap sensitive: will not explode from a detonator or fuse alone. A cap-sensitive primer is needed first, which is why a booster goes into the hole. These are used only in opencast mines.
- Booster cartridges: Pentolite, Primex. Booster explosives: Opencast Gelatine (OCG), Navbharat Prime and similar.
How much booster goes in?
The booster cartridge is about 0.25% of the explosive charged in the hole. The booster-to-slurry ratio is 30:70, 25:75 or 20:80, decided by the density of the explosive and the strata. The booster can go in before or after the main explosive, but it is never mixed with it. The detonating cord is tied to the booster.
2. Blasting Accessories
Detonating cord (Cordtex)
A strong plastic tube about 5 mm in diameter, filled with PETN or TNT at about 11 g per metre. It comes in rolls of 100, 200 and 300 m, and its velocity of detonation is about 7000 m/s. In deep-hole blasting, a booster is tied to the cord in each hole, the cords are joined on the surface, and a single detonator goes at the free end. The detonator is fired with an exploder, so the cord goes off and every hole fires together. It is very safe, and you do not need a detonator in every hole.
Detonating relay
Used when you want to blast a hole or a line of holes separately. Instead of a delay detonator, a relay is clipped into the cord between two holes. It holds delay material, and comes in 25, 50, 75, 100 and 150 ms intervals.
Nonel (non-electric detonator)
Made in India by two companies under different names: Excel and Raydet. A Nonel set is two detonators joined together:
- Down the hole (DTH): goes inside the hole. Delays of 100 to 500 ms.
- Trunk line delay (TLD): sits on the surface between holes. Delays of 17 to 150 ms.
The plastic tube carries 14 to 16 mg per metre of chemical mix, with the delay detonator on one end and a clip on the other. Tubes are bought in the length you need, and they must never be cut shorter.
Why Nonel is popular:
- It is today’s best option for controlled blasting, with very little ground vibration and less flyrock.
- Rock breaks into smaller pieces, so less secondary blasting.
- Most holes get two free faces, so more of the explosive energy goes into breaking rock. Explosive cost can drop by up to 20%.
- No toe is left on the bench.
- It works well in deck blasting, with no cut-off.
- Lightning is no danger to it.
3. Drilling and Charging Terms
Subgrade drilling and toe
When the upper bench is blasted, a bit of rock can be left standing at the bottom of the bench. That stub is called the toe. To avoid it, blast holes are drilled about 10% deeper than the bench height. That extra depth is subgrade drilling.
Deck charging
Some benches have hard rock in places and soft rock in others. Here, about half to two-thirds of the explosive goes at the bottom of the hole, and the rest is placed near the hard layers. Stemming is put between the charges, and each deck gets its own detonating wire. Rock breaks evenly into small pieces.
Muffled blasting
To stop rock from flying, the blast area is covered with wire or nylon netting, and sandbags are stacked on top.
Secondary blasting
Deep-hole blasting sometimes leaves large boulders. They are broken again by one of three methods:
- Pop shooting: a hole is drilled into the boulder and blasted. Special Gelatine-90 is used.
- Plaster shooting: no hole. The explosive is placed in a crevice on the boulder and covered with wet clay. Plaster Gelatine is used, because it creates strong vibration that breaks the rock.
- Snake holing: a gap is made under the boulder, explosive is placed there and packed with soil. P1 or Special Gelatine is used.
Deep hole
A hole of 3 m or more is a deep hole. In opencast mines, holes are normally 100 to 350 mm in diameter, depending on bench height and how hard the rock or coal is.
4. Burden, Spacing and Charge Calculations
Burden is the distance from the free face of the bench to the first row of holes, and also the distance between one row and the next. Spacing is the distance between holes in the same row.
| Rock type | Burden | Spacing | Explosive per m³ |
|---|---|---|---|
| Hard rock | hole diameter × 25 | 1 × burden | 0.4 to 0.5 kg |
| Medium rock | hole diameter × 30 | 1.25 × burden | 0.3 kg |
| Soft rock / coal | hole diameter × 35 | 1.5 × burden | 0.2 kg |
How much material does one hole break? Multiply spacing × burden × hole depth, all in metres, and you get cubic metres of coal or rock per hole. For example, 7.5 m × 6 m × 10 m = 450 m³ in medium rock, which at 0.3 kg/m³ needs about 135 kg of explosive (illustrative numbers).
5. Sleeping Holes
A sleeping hole is one that is charged but not blasted on the same day. Large opencast mines need them, because blasting daily means shifting the big machines out every day, and that hurts production. So many holes are prepared and fired together. But too many holes cannot be charged in a day, and holes left for long get damaged. Sleeping holes need special permission from DGMS.
Precautions for sleeping holes:
- At least two lines of holes stay uncharged between holes being charged and the drilling machine.
- No fire, welding, beedi or matches within 30 m.
- Red flags mark the area, and red lights at night.
- Stemming is done right after charging.
- The top end of the detonating fuse is covered by the stemming.
- No detonator is used inside a sleeping hole.
- Maximum duration: 7 days on a shovel bench and 15 days on a dragline bench.
- Records are kept, and the work goes on under an assistant manager.
- Detonating fuses of the holes are joined only on the day of blasting.
6. Special Conditions
Hot strata
Strata hotter than 80°C count as hot strata. Precautions:
- Use only slurry explosive.
- Measure the temperature of every hole with a thermometer. If it is above 80°C, fill the hole with water and leave it for 24 hours.
- If the water drains away, mix bentonite into it and refill.
- If it still drains, place asbestos pipes in the hole and fill the pipe with water.
- After 24 hours, measure again. Charge only if the temperature is below 80°C.
- Use only detonating fuse.
- Blast within two hours of charging.
Electric storm
- Stop charging at once.
- Take all explosives lying on the surface to a safe place.
- Bury the detonating fuse ends of the holes in stemming.
- If connections are already made, cut and separate the fuses and bury them in the holes’ stemming.
- Remove iron mesh or plates from the area.
- Move everyone to a safe place away from the blasting area.
7. Safety Routine Around a Blast
The danger zone for blasting in opencast is 500 m. Everyone must be moved out of it before the shot.
Precautions to prevent blasting accidents
- Danger zone: mark the 500 m radius with red flags. Post guards at main entry points, and nobody enters during the blast.
- Safety flag: before charging, clear all vehicles from the area and 50 m around it, hoist a red flag and put up a danger board.
- Training: everyone connected with blasting gets special training.
- Supervision: explosives are used under an experienced overman or assistant manager.
- Time of blasting: in daylight only, ideally around midday when fewer people are outside.
- Charging plan: make a plan so that charging and stemming are systematic and no hole gets more explosive than needed.
- Muffled blasting: use it wherever it is needed.
- Welding and fire: not allowed within 50 m of the blasting area.
- Warning to people: take into account houses and structures near the danger area and arrange their safety.
- Blasting shelter: choose a proper shelter for the shotfirer.
- Same-day firing: blast every hole on the day it is charged. If that is not possible, take permission from the Regional Inspector.
- Siren: sound it 10 minutes before the blast, to warn everyone. It sounds three times, one minute apart.
- All clear: after the blast, everyone stays put until the area has been fully checked. If a misfire is found, clear it first and only then give the all-clear.
Hazards of deep-hole blasting
- Flyrock: can injure workers and nearby villagers, and damage machines, houses and property.
- Ground vibration: can weaken benches and damage nearby buildings, bridges, roads and dams.
- Fumes: a lot of explosive means a lot of fumes that pollute the air and harm anyone exposed.
- Dust: blasting a large area raises heavy dust that can cause illness.
- Noise: the very loud sound can damage the ears of people in shelters nearby.
Controlling flyrock and vibration
- Design the hole pattern so the maximum energy goes into breaking rock.
- Do not charge more explosive than needed.
- Stem the hole right up to the top and tamp it well.
- Use millisecond delay detonators.
- Never use small stones as stemming.
- Clear all loose stones from the blasting area, and loose rocks from the bench edge.
- Use deck charging where the bench has layers of weak and hard rock.
- Use muffled blasting where required.
- Use controlled blasting, by any one of these methods:
- Line drilling: a line of holes beyond the blast area, as deep as the blast holes, spaced 2 to 4 times the hole diameter, and not charged.
- Presplitting: holes at the limit of the blast area, as deep as the blast holes, spaced 6 to 12 times the hole diameter, lightly charged and fired before the main blast, so the ground cracks there and vibration stops at that line.
- Nonel: non-electric detonators, with careful attention to the delays between holes and between rows.
For design-side thinking behind these rules, see our post on blast design parameters in surface mining.
8. What to Do About a Misfire
Method A: use the fuse. Look for the detonating fuse of the misfired hole. If found, connect it to another detonating fuse and blast. The misfire is cleared with that blast. If the fuse cannot be found, or blasting does not clear it, use one of the methods below.
Method B: remove the material with a shovel and reach the hole, taking these precautions:
- Fit wire mesh in front of the shovel cabin.
- Use only two dumpers. Only one is near the shovel at a time, parked with its cabin on the side away from the misfire. The second one is called in only after the first has left loaded.
- Everyone not needed for the job is moved out of the area.
- The work is supervised by an overman or assistant manager.
- The supervisor sits in a shelter with a clear view of the shovel’s work and carries a whistle for signals.
- Work is done in daylight only.
- The shovel lifts rock or coal and moves ahead gradually, searching for the hole near it.
- If explosive is seen, remove it. If it cannot be removed, fit a booster and blast.
- If the broken hole is not found below the bench, or the explosive is not visible, this method will not clear the misfire. Use another method.
Method C: relieving hole from the surface.
- Remove rock or coal around the misfired hole with a dozer, taking special care of the detonating fuse.
- Drill a hole 3 m away from the misfired hole, only as deep as the explosive filled in the misfired hole.
- Charge and blast the relieving hole.
- Remove the rock or coal with a dozer again and look for the misfired hole.
- When found, take out some of its explosive, charge a booster, and blast it with detonating fuse.
Method D: compressed air (instead of Method C). Clear the surface rock with a dozer and find the hole. Blow out its stemming with compressed air, charge a booster and blast without stemming. Do not use this method if the booster was charged on top of the explosive.
Numbers to Memorise
| Item | Value |
|---|---|
| ANFO composition | 94% ammonium nitrate + 6% diesel |
| Booster quantity | 0.25% of the charge; booster : slurry 30:70, 25:75, 20:80 |
| Detonating cord | 11 g/m, 7000 m/s, rolls of 100/200/300 m |
| Relay delays | 25, 50, 75, 100, 150 ms |
| Nonel DTH / TLD | 100–500 ms / 17–150 ms |
| Subgrade drilling | 10% deeper |
| Deep hole | 3 m or more; diameter 100–350 mm |
| Burden | 25 / 30 / 35 × hole diameter (hard / medium / soft) |
| Spacing | 1 / 1.25 / 1.5 × burden |
| Charge per m³ | 0.4–0.5 / 0.3 / 0.2 kg |
| Sleeping holes | 7 days (shovel bench), 15 days (dragline bench); no fire within 30 m |
| Hot strata | above 80°C; water for 24 h; blast within 2 h of charging |
| Danger zone / safety flag | 500 m / 50 m |
| Siren | 10 minutes before; 3 times, 1 minute apart |
| Line drilling / presplitting spacing | 2–4 × / 6–12 × hole diameter |
| Relieving hole for a misfire | 3 m away from the misfired hole |
Test Yourself