Indian Minerology: Global Mining Engineers Blog; Miners Study Hub. Master open-cast and underground operations, safety rules, machinery tips, quizzes and career guides worldwide. Subscribe for updates! #MiningEngineersBlog, #OpenCastMining, #UndergroundMining, #IndianMinerology, #WorldWideMining, #Mining Engineering Blog | DGMS Preparation | Open Cast Mining
Excavator hourly production calculation is a very important topic in opencast mining for production planning, cost estimation, and equipment selection.
Excavator production is the quantity of material excavated and loaded by an excavator in one hour. It is generally expressed in cubic meter per hour (m³/hr) or tonnes per hour (TPH).
Production = Bucket Capacity × Fill Factor × Cycles per Hour
Cycles per Hour = 3600 / Cycle Time (seconds)
TPH = Production (m³/hr) × Material Density
Bucket Capacity = 5 m³
Fill Factor = 0.9
Cycle Time = 25 seconds
Material Density = 1.8 t/m³
= 3600 / 25 = 144 cycles
= 5 × 0.9 × 144 = 648 m³/hr
= 648 × 1.8 = 1166 tonnes/hr
It varies from 300 m³/hr to 1500 m³/hr depending on machine size and working conditions.
Hydraulic front shovel excavators are best for large opencast mines.
Excavator hourly production calculation helps mining engineers to optimize productivity and reduce cost. Accurate data and proper calculation are essential for efficient mining operations.